Elapsed Durations #

An ordinary duration is measured in working time. A three-day task on a Monday-to-Friday, eight-hours-a-day calendar takes 24 working hours, and if it starts on Thursday it finishes on Monday — the weekend does not count.

An elapsed duration is measured in clock time. It counts continuously, 24 hours a day, 7 days a week, through weekends, holidays, and every non-working exception on the calendar.

Use it for anything that does not care whether your team is at work: concrete curing, paint drying, a test soak, a regulatory waiting period, or shipping in transit.

Entering an Elapsed Duration #

Type the duration with an e before the unit:

You type You get
3d 3 working days
3ed 3 elapsed days — 72 clock hours
2ew 2 elapsed weeks — 14 calendar days
8eh 8 elapsed hours

The units are min, h, d, w, and m — minutes, hours, days, weeks, months — and every one of them takes the e. The abbreviations are translated, so in a non-English interface use that language's unit letters; the e marker stays.

You can also use the Elapsed checkbox instead of typing, in the duration editor of the Task Properties dialog. Its tooltip is the definition:

Elapsed. When checked, duration counts continuously (24/7) instead of only during working hours defined by the calendar.

Ticking or unticking the box keeps the number you can see and changes what it means: 3d becomes 3ed. It does not silently convert 3 working days into the equivalent number of elapsed days.

What an Elapsed Unit Is Worth #

Elapsed units ignore your project calendar and use fixed calendar arithmetic:

Unit Elapsed value
1 elapsed day 24 hours
1 elapsed week 7 days = 168 hours
1 elapsed month 30 days = 720 hours

Compare that with working units, which come from Project Properties — by default 8 hours a day, 5 days a week, 20 days a month. So 1w is 40 working hours while 1ew is 168 clock hours.

Elapsed Lag on a Dependency #

The same idea applies to the lag on a dependency, and this is where it matters most. "Start the next task three days after this one finishes" usually means three calendar days, not three working days — otherwise a Friday finish pushes the successor to Wednesday.

In the Predecessors tab of Task Properties, each link has its own Elapsed checkbox next to the lag, with the same meaning:

When checked, lag time counts continuously (24/7) instead of only during working hours defined by the calendar.

You can type it directly too: a lag of 3ed is three calendar days.

Import and Export #

Elapsed durations and lags are part of the Microsoft Project format and survive a round trip in both directions. A 3ed duration imported from Microsoft Project stays 3ed, and exports back as an elapsed duration.