Resource Leveling #

It's easy to accidentally assign more work than a person can handle in a day. Leveling automatically shifts tasks so no one is overloaded, though it may extend your project's finish date.

Overallocated Resources #

A work resource can be overallocated, meaning it has more work assigned than it can complete based on its calendar and availability. For example, if your project has two tasks, each with a duration of one day and no dependency between them, both assigned to the same work resource, the resource is overallocated. The resource has to do two days of work in one calendar day. To resolve this, simply link the two tasks with a dependency.

If a task has overallocated resources assigned, Ingantt shows a special icon for it in the list of tasks.

If a resource is overallocated, Ingantt shows a special icon for it in the Resources view and the Resource Usage view.

Additionally, Ingantt counts such tasks and resources and shows the numbers in the navigation drawer.

Auto-Leveling #

Dependencies between tasks control their position on the timeline. In larger projects, it's easy to miss a dependency — resulting in multiple tasks assigned to the same work resource being scheduled at the same time. The resource becomes overallocated, and Ingantt notifies you with special icons in the task and resource lists.

You can resolve overallocation manually by setting dependencies or constraints to move some tasks so that work is not done simultaneously.

An alternative way to resolve overallocation is auto-leveling. If you choose to Auto-level resources in the Project menu, Ingantt automatically shifts some tasks further on the timeline to prevent resource overallocation. You can clear these automatic adjustments by choosing Clear leveling in the Project menu.

The auto-level command offers three scope options:

How Auto-Leveling Works #

When you run Auto-level resources, Ingantt resolves overallocations by delaying or splitting tasks. It does not reassign resources or change assignment units.

The algorithm identifies days where a resource has more assigned work than its capacity allows, then decides which competing tasks to delay. Each task is scored based on several factors — tasks with higher scores are protected from delay:

Factor Effect
Dependencies Tasks that are predecessors to other tasks are protected
Slack Critical or near-critical tasks (less slack) are protected
Priority Tasks with a higher Priority value are protected
Constraints Tasks with scheduling constraints are protected
Start Date Earlier tasks are somewhat protected
Duration Longer tasks are somewhat protected

The task with the lowest score is delayed to resolve each conflict. The process repeats until all overallocations are resolved or no further delays can be applied.

Auto-leveling may extend the project's finish date. It resolves as many overallocations as possible, but some may remain if constraints prevent further delays.

Leveling Options #

Configure leveling behavior in the Leveling Options dialog, accessible from the Project menu:

Exempt from Leveling #

The following tasks and resources are never affected by auto-leveling:

Re-Leveling and Clearing #

Each time you run Auto-level resources, any previous leveling is automatically cleared first. Leveling always starts from a clean, unleveled schedule to prevent delays from stacking.

If you modify the schedule after leveling (add tasks, change dependencies, etc.), the existing leveling delays are preserved but may no longer resolve all overallocations. Run Auto-level resources again to re-level the updated schedule.

To remove all leveling delays and return to the original CPM-calculated schedule, choose Clear leveling from the Project menu.

Leveling Gantt #

After you run auto-leveling, a Leveling Gantt toggle button appears in the Gantt chart area. When enabled, it draws green bars at the pre-leveled positions — where tasks were before leveling — while the standard task bars remain at their current leveled positions. This lets you compare the original schedule with the leveled schedule to see how much each task was delayed.

The toggle is only visible when the project has leveling data and is automatically hidden when you clear leveling.

Priority #

The Priority field is available on the Leveling tab of the Task Properties dialog. It accepts an integer value from 0 to 1000, with a default of 500.

Priority is used by the auto-leveling algorithm to decide which tasks to delay when resolving resource overallocations. Tasks with a higher priority are less likely to be delayed:

Set Priority to 1000 for tasks that must never be moved by auto-leveling, such as tasks tied to external deadlines or fixed commitments.